Due to a change in the data center, a shutdown is required to move the visualization server to another Rack.
This shutdown will cause all VM's to be off-line during the time of the data center work.
- Scheduled date: 2017-04-24
- Scheduled start time: approx. 16:00
- Expected duration: approx. 2-4 hours
To follow the progress of the scheduled maintenance, visit https://status.cm.tinned-software.net/.
2017-04-24 19:00:
Most services restored. VM with full-disk-encryption are not yet up and running.
2017-04-24 20:50:
All systems operational again. VM's requiring a disc-encryption password are booted.